Setting up the Project Service Create sales proposals from leads in Project Service Create a project in the Project Service Plan your project with Project Service Project Service Manage and close projects Project Service resource allocation and shipping units Troubleshoot PSA Schedule Board Editing WBS in Project Service and Microsoft Project Update the Project Service working template
2017.08.23 | managing-projects-in-dynamics-365/

Project Service resource allocation and shipping units

Author:Takafumi Noguchi

linkedIn

When you create a project in Dynamics 365 for Project Service Automation and assign team members, the calculation of the assigned time for the assigned members is a bit complicated, so I will show you how it works.

Resource “allocation method”.

When you assign resources as a team member of a project, you have a choice in the field called “Assignment Method”.

If you check the official page, you will see that it means the following.

  • All Capacity reserves the full capacity of the resource for the specified start and end dates.
  • The capacity percentage reserves resources as a percentage of the resource capacity for the specified start and end dates.
  • By Time - Equal distribution reserves resources for a specified number of hours, equally distributed per day from a specified start date to an end date.
  • By Time - Advance reserves the resource for a specified number of hours, with the hours advanced per day from the specified start date to the end date.
  • None will add resources to the team, but will not create reservations to absorb this capacity.

Quote: How do I assign resources to a task?

The above explanation is a little difficult to understand, so I tried to represent it with a diagram.

The above figure shows the resources reserved for two days (8 hours x 2 = 16 hours) on 02/07/2019 - 02/08/2019, using the respective allocation methods. This 8-hour period is set in the work template.

This 16-hour period affects the “total capacity” and the “percentage of capacity”.

  • In the case of “full capacity,” you would be booking 100% of the time, so 8 hours over two days, each for a single project.
  • In the case of “Percentage of Capacity”, set the percentage, in this case 50%, so 4 hours are reserved over 2 days.

In the above figure, the period is set to 12 hours. In the figure above, the period is set to 12 hours.

  • In the case of “By Time - Equal Distribution”, 12 hours will be distributed evenly over two days, so 12 hours / 2 days = 6 hours.
  • In the case of “By Time - Advance”, 8 hours are assigned to the previous day, 2/7, and the remaining 4 hours are assigned to 2/8.

As you can see, the time reserved for a resource differs depending on the setting of the allocation method, so please use it well.

About WBS shipping units

Once you have reserved a certain amount of time as a member of a project as described above, you can assign that time to a task in the WBS. At that time, there is an item called “Shipping Unit” as shown in the figure below.

This “shipping unit” is linked to the “man-hour” and “period” of the WBS. For example, let’s assume that we have a development task with a “Man-hour” of 40 hours, a “Duration” of 5 days, and a “Shipping Unit” of 100%, as shown below.

If you want to assign two programmers from different companies to this development task, you can use the “Add” button to add two programmers with a “Shipping Unit” of 100%, and the “Man-hours” will be assigned every 50%.

What if the workload of the two programmers is 80:20? Change the “Shipping Unit” percentage.

If multiple resources are assigned to a task that is allocated in this way, you can adjust the allocation time for each resource in the “shipping unit”.

For shipping units of resources that are only 50% allocated

The basic idea is to allocate 100% of resources to a single project, but when you are concurrently working on multiple projects like a PM, you need to distribute the resource allocation rate. For example, let’s say you are a PM as shown in the figure below, and you allocate 50% of the resources to the tasks in the WBS.

The “man-hours” for the “Fit & Gap” task in the WBS is 40 hours, and if we assign “Shipping Units” at 100%, 40 hours should originally be allocated.

But here’s the nice thing about Dynamics 365 for Project Service Automation: when you check the team for the project, the “Allocated Time” is automatically calculated as 20 hours (40 hours x 50%).

You can assign tasks without worrying about the percentage of resources participating in the project. I personally think this is a well-designed feature.

The behavior is a bit confusing regarding resource allocation and shipping units for project members, so I hope this will be helpful. That’s all for this time.
 

Dynamics 365 Blog / managing-projects-in-dynamics-365 /psa-assign-team-members

Those who read this article have read other articles like this.

Popular articles